Riders along Flinders Lane may encounter underground electricity cable works at Queens Street beginning next week.
As part of works to upgrade Little Queen Street Zone Substation, CitiPower will be completing works on Queen Street between 19 September and 14 October 2025 which will close Flinders Lane between Queen and Market streets.
Undertaken in stages, works will take place in Queen Street northbound between 9.30am and 4pm weekdays on the following dates: Monday 19 to Wednesday 24 September, Tuesday 30 September to Wednesday 1 October, and Wednesday 8 to Tuesday 14 October.
While sections of Flinders Lane are closed, the traffic control team will manage local access from Market Street, with vehicles, cyclists and pedestrians guided around the work area.